Step 1 of 7 · Week 1–2 · Client + Saksham Powergen
Load & feasibility study
We study your bills to size your share of an SPV plant so you consume at least 51% of its output.
Pick a model and press play.
Solar park
You 26% · Developer 74%
Solar units ⚡
State grid
Grid charges · surcharge exempt
Adjusted in bill
Your factory
Pays per-unit tariff
Step 1 of 7 · Week 1–2 · Client + Saksham Powergen
We study your bills to size your share of an SPV plant so you consume at least 51% of its output.
10 key clauses for Group Captive. Tap one to read it three ways.
In plain English
You must own at least 26% of the plant company and use at least 51% of its power, in proportion to your shares.
How you are protected
The developer must keep the structure compliant; if it fails because of the developer, it pays the surcharge.
Sample contract wording
The Captive Users shall collectively hold not less than 26% of the ownership and consume not less than 51% of the aggregate electricity generated, determined on an annual basis, as per Rule 3 of the Electricity Rules, 2005.
Sample wording is illustrative; final clauses are settled by both parties' legal teams.
Move the sliders. The recommendation updates instantly.
Stake you want in the plant
Plant needed: 1,000 kWp · Project cost ₹4.50 Cr
Indicative: 4 kWh/kWp/day, ₹45,000/kWp, typical landed costs. Actual figures depend on state charges and site.